- Services
- Decommissioning
- Well Abandonment
- Life of Field
- Controlled Flow Excavation
- Project management
- Worldwide partnerships
- Bespoke engineering
- Equipment overhaul and recertification
- Offshore technicians
- JFS complementary services
- Equipment
- Subsea tooling
- Winches
- Marine cranes
- Fluid solutions
- Associated deck equipment
- Controlled Flow Excavation Tools
- Ingersoll Rand
- Man riding winches
- Utility winches
- Hoists
- BOP handling systems
- OEM spare parts
- Ingersoll Rand service centre
- Ingersoll Rand power tools
- About
- Our Values
- Careers
- Apprenticeships
- Global locations
- QHSE (Quality, Health, Safety and Environment)
- Cutting equipment
- Recovery equipment
- Coating removal equipment
- Subsea pumps
- Subsea ancillary equipment
- Torquing and bolting
- Spare parts and consumables
- Subsea drills
- Subsea cleaning powertools
- Subsea breakers
- Positive displacement pumps/HT400
- Centrifugal pumps
- Jetting pumps
- Umbilical reelers and associated equipment
- Air compressors
- Fairleads
- Hydraulic power units (HPUs)
- Launch and recovery systems (LARS) / A-frames
- Overboarding sheaves
- Hot wash unit
- James Fisher and NMDC Group sign strategic agreement
- Supporting our local community
- Energy Voice - James Fisher Decommissioning
- James Fisher to address needs of expanding decommissioning market with launch of dedicated business line
- Archive
- Supplying pumping equipment to raise the Costa Concordia
- Equipment spreads for Hess South Arne and IVRR
- Supporting Fugro Subsea Services Ltd. with equipment deployment in the North Sea
- Mobilising hydraulic winch package for Technip
- Taqa Harding DSV campaigns
- Dredging for Subsea 7 in the North Sea
- Full back deck provision for Technip IRM campaign
- Subsea 7 - BP West Nile Delta gas development
- Subsea umbilical removal for the Judy platform
- Supporting Bibby Subsea with IRM works
- Pull-in winch package for Technip/Chevron Bangka project
- Supplying hydraulic winch packages for Quad 204 FPSO project
- Installing and commissioning FPSO winch package alongside Bibby Offshore
- Provision of deck and subsea equipment for Hibernia Southern Extension project
- Gryphon Alpha FPSO winch and line monitoring package
- Enabling riser pull-in on the Dunlin Alpha platform
- BP Clair fibre optic installation
- Electrical umbilical pull-in for Callater Field development
- Undertaking preventative winch maintenance for Ensco
- JFO provides bespoke solutions on complex project off the Ivory Coast
- James Fisher Offshore supports Subsea 7 in Gorgon project
- Recovery and reinstallation of Ocean Installer mooring lines
- Nemo Link UXO Investigation
- Lancaster EPS Project
- TechnipFMC Enquest Kraken
- TechnipFMC/Repsol IRM
- Subsea 7 BP Atoll
- Cutting, dredging and recovery demonstration
- Premier Oil Balmoral Abex - Decommissioning
- Safaniya Demolition works
- DeepOcean Ghana, TEN project
- Abrasive Water Jet Cutting Case Study
- Safaniya Jacket Removal
- Seven Kestrel IRM
- Bokor Phase III Redevelopment
- Linear Winch Case Study
- Talos Bulleit
- Well severance UKCS
- *Update* Safaniya Jacket Removal
- Sapura / Chevron Thailand jacket and pipeline removal
- CFE Q1 2021 update
- JFO Life of Field - Riser installation UKCS
- Life of Field update Q2 2021
- Controlled Flow Excavation services for Renewables
- Multistring Conductor Cut and Recovery
- Pipeline cut and recovery, Arabian Gulf
- Jacket Removal, Safaniya, KSA
- Slipover jacket removal from James Fisher Decommissioning
- USA Offshore Wind Farms
- Abrasive cutting trial at National Hyperbaric Centre Aberdeen
- Shore Pull Kingdom of Saudi Arabia
- James Fisher Decommissioning - Gyda jacket decommissioning
- Jacket repair case study
- Installation of flexible risers case study
Pull-in winch package for Technip on the Chevron Bangka project
Scope of works:
Technip’s scope of work was to provide full EPIC subsea project service for the two well tie-backs to the West Seno platform in the Makassar Strait, with the exception only of the supply of the subsea connectors and PLEM valves.
- Execute full EPIC of 9.5” flexible flowline and riser system, including flow assurance validation
- Execute full EPIC of two production jumpers for subsea wells
- Execute full EPIC of static and dynamic umbilical section
- Installation of a PLEM
Scope of supply:
James Fisher Offshore (JFO) provided services for one pull-in winch package which included the following:
- 70Te hydraulic winch with spooling gear (level wind)
- Remote control
- Zone 2 diesel driven hydraulic power units (HPUs)
- Running line monitor system
- 60Te vertical and horizontal deck sheaves
The equipment was mobilised to Balikpapan, Indonesia then offshore onto the West Seno floating production unit (FPU).
Through the James Fisher Offshore project office in Singapore, JFO attended several project meetings with Technip in their Asia Pacific office to ensure successful project delivery.
A lead JFO technician and two operators were utilised for 24 hours operational coverage, during both the equipment commissioning and pull-in phases.
For more information on pull-in winch package capabilities contact James Fisher Offshore.
Download the 'Pull-in winch package for Technip / Chevron Bangka project' case study.